Patna Gaya Dobhi Fourlane Will Not be Completed Even After 1 Year From The Deadline

Patna Gaya Dobhi Fourlane Will Not be Completed Even After 1 Year From The Deadline

Latest News
Due to slow work progress in Patna Gaya Dobhi Fourlane, it will not be completed even after 1 year from the deadline. The latest Patna Gaya Dobhi Fourlane deadline was set for 31 March 2023. Patna Gaya Dobhi Fourlane Road Project is a long pending road project in Bihar. The National Highways Authority of India (NHAI) granted a contract worth Rs 2,015 crore to IL&FS Engineering and Construction Company Limited on April 24, 2014, to implement the four-lane project. The deadline set by NHAI for completing the four-lane section of the 127 km stretch of the national highway between Dobhi and Patna was April 9, 2018. The April 2018 deadline has expired, but hardly 15 per cent of the work has been done on the Patna-Gaya-Dobhi four lane road project. The Patna-Dobhi four-lane proje...